Waterworks
WSD Contract No. 13/WSD/16
Client
Water Supplies Department
2017-2021 (in progress)
Laying about 10 km of DN1200 fresh water main, connecting the proposed desalination plant at TKO to the existing TKO fresh water primary service reservoir.
- 8.3 km water main using Open Trench Method along carriageway and footpath.
- 1.6 km water main using Trenchless Method.